News
Update

15 October 2019 - Structure topped out and construction programme well advanced.

The building was topped out at the end of September and construction is progressing at full speed and ahead of schedule.
The crane is coming down within a week as its mission has now been completed.

As can be seen from the latest picture posted below, balustrades are at Level 7 and windows are being installed at level 10.
Internal fit-out is progressing floor by floor in different stages so that Level 3 is at painting and Level 10 is at plastering.

We are proceeding with a staged sub division so that all levels up to and including Level 6 are expected to be ready for settlement in December 2019. Please commence your finance applications soon so that you will be ready for settlement.

Click to view current photograph - External Facade Shot

News
Update

8 September 2019 - Levels 9, 10 & 11 slabs poured.
Windows installed up to Level 7 and internal fit out and services proceeding.

Level 11 slab, which is the main building rooftop below the Sky Home Penthouses, has now been formed and poured at the Northern end and the Southern end slab will follow next Wednesday 11 September 2019.

This now places our builder, Hamilton Marino Builders, a full two weeks ahead of schedule and augurs well for the programmed final completion date for the entire project of 29 April 2020.

Of course there will be earlier completions scheduled for lower levels but 29 April is an overall latest expected completion date including the 5 two level Sky Homes at levels 12 & 13.

Some of the other milestones currently in the building are:

Kitchens and flooring being installed at Level 2;
Plastering now completed up to and including level 3;
Balustrades now completed partly up to level 4; and
Windows are being installed at Level 7.

We will update the web site further at the end of September when we expect that the full structure will be totally complete and the crane will come down early in October.

Click to view current photograph - Level 11 Slab Click to view current photograph - Building from Doncaster Rd Click to view current photograph - Building from Elgar Rd Click to view current photograph - Building from Elgar Rd Click to view current photograph - Building from Doncaster Rd

News
Update

7 August 2019 - Levels 6, 7 & 8 slabs poured.
Windows installed in Levels G, 1, 2 & 3 and internal fit out and services proceeding.

The concrete structure of the building is now complete up to Level 8. Windows have been installed up to and including level 3. Plastering is up to Level 2 and internal wall framing is proceeding on higher levels. Services (plumbing & electrical) are proceeding to move up through the building.

Please continue to check this site periodically for updates.

Click to view current photograph - Level 8 Click to view current photograph - Building from Doncaster Rd

News
Update

15 July 2019 - Levels 3, 4 & 5 slabs poured, Level 6 slab in progress, windows being installed in Levels 1-3 and internal fit out and services proceeding.

The concrete structure of the building is now complete up to Level 5 with Level 6 slab well underway with columns and most of the formwork in place. Windows are currently being installed in Levels G, 1 & 2. Internal wall framing is up to Level 2. Services (plumbing & electrical) are proceeding to move up through the building.

As previously advised, the build will move much faster now that that the building has risen out of the ground.

Please continue to check this site periodically for updates.

Click to view current photograph - Level 5

News
Update

3 June 2019 - Level 1 & 2 slabs poured, Level 3 slab in progress, services trades underway.

Level 1 & 2 slabs have now been poured and level 3 slab is well underway with columns and most of the formwork in place. Services trades have also commenced onsite to start rough in of plumbing and electrical infrastructure.

As previously advised, the build will move much faster now that that the building has risen out of the ground.

Please continue to check this site periodically for updates.

News
Update

10 May 2019 - Basements completed,
Ground floor slab poured and
Level 1 slab in progress

The newly installed robotic concrete boom has been used for the first time onsite to pour the super sized ground floor slab.

The structure for the 4 basement carpark levels is complete and the ground floor slab has been completed.

Basements, foundations and ground floor slabs are complex and time consuming so the build will move much faster now that that the building has risen out of the ground. Columns and formwork for level 1 have commenced.

Please continue to check this site periodically for updates.

Click to view Ground Floor - concrete pour Click to view Level 1 - slab formation

News
Update

14 December 2018 - Crane up, basement excavation completed
& foundations underway

The tower crane has now been erected onsite.

Excavation of the basement has been completed and all retaining walls have been constructed.

Foundations and preparation for slab on ground are well underway.

Hamilton Marino Builders have now commenced onsite.

Please continue to check this site periodically for updates.

Click to view crane photo 1 Click to view crane photo 2 Click to view crane photo 3 Click to view crane photo 4 Click to view basement photo 1 Click to view basement photo 2 Click to view basement photo 3 Click to view basement photo 4

News
Update

16 October 2018 - Excavation reaches third basement
& Hamilton Marino Builders Appointed

Excavation is now progressing into the third basement level and beyond.

The top down slab/platform which will form the platform which the loading and unloading vehicles will use, has now been formed and poured and can be seen in the picture below.

We expect to reach the bottom level of the car park by the middle of November.

Hamilton Marino Builders have been officially appointed as builders and they will take over as soon as the excavation of the basement is completed.

Please continue to check this site periodically for updates.

Click to view photo 1 Click to view photo 2 Click to view photo 3

News
Update

10 September 2018 - Excavation Proceeding
& Hamilton Marino Builders Appointed

The piling and retention works have been completed for the site and excavation is proceeding.

Hamilton Marino Builders have also been formally appointed as builders.
Please continue to check this site periodically for updates.

Click to view photo

News
Update

17 May 2018 - Construction Management Plan Approved

Following approval of the Construction Management Plan by City of Manningham and Vicroads, piling and excavation of the basement carpark has now commenced onsite.
Please continue to check this site periodically for updates.

Click to view photo 1 Click to view photo 2

News
Update

06 April 2018 - The site has now been fully demolished after it took more than two months to obtain approval from the power authorities to abolish power in an abandoned building

We have served protection works notices and have the piling rig and excavators waiting on site to commence construction works.
We are currently awaiting approval of our Construction Management Plan which was lodged with City of Manningham in mid-December following which works will commence immediately.

Click to view photo 1 Click to view photo 2

600 Doncaster Road, DoncasterDelta Property group

DisclaimeruPrivacy policyuDue Diligence

Please note while every care is taken to ensure the contents of this website are correct, this information is to be used as a guide only. All images (including artist’s impressions) and plans are indicative only. Prospective purchasers should rely on their own enquiries, legal advice and the contract of sale. This site was completed prior to the completion of the design and construction of the project, therefore design, dimensions, fittings and specifications are subject to change. All areas are provided in accordance with the Method of Measurement for Residential Property provided by The Property Council of Australia. This does not represent the area on Title.