News
Update

7 August 2019 - Levels 6, 7 & 8 slabs poured.
Windows installed in Levels G, 1, 2 & 3 and internal fit out and services proceeding.

The concrete structure of the building is now complete up to Level 8. Windows have been installed up to and including level 3. Plastering is up to Level 2 and internal wall framing is proceeding on higher levels. Services (plumbing & electrical) are proceeding to move up through the building.

Please continue to check this site periodically for updates.

Click to view current photograph - Level 8 Click to view current photograph - Building from Doncaster Rd

News
Update

15 July 2019 - Levels 3, 4 & 5 slabs poured, Level 6 slab in progress, windows being installed in Levels 1-3 and internal fit out and services proceeding.

The concrete structure of the building is now complete up to Level 5 with Level 6 slab well underway with columns and most of the formwork in place. Windows are currently being installed in Levels G, 1 & 2. Internal wall framing is up to Level 2. Services (plumbing & electrical) are proceeding to move up through the building.

As previously advised, the build will move much faster now that that the building has risen out of the ground.

Please continue to check this site periodically for updates.

Click to view current photograph - Level 5

News
Update

3 June 2019 - Level 1 & 2 slabs poured, Level 3 slab in progress, services trades underway.

Level 1 & 2 slabs have now been poured and level 3 slab is well underway with columns and most of the formwork in place. Services trades have also commenced onsite to start rough in of plumbing and electrical infrastructure.

As previously advised, the build will move much faster now that that the building has risen out of the ground.

Please continue to check this site periodically for updates.

News
Update

10 May 2019 - Basements completed,
Ground floor slab poured and
Level 1 slab in progress

The newly installed robotic concrete boom has been used for the first time onsite to pour the super sized ground floor slab.

The structure for the 4 basement carpark levels is complete and the ground floor slab has been completed.

Basements, foundations and ground floor slabs are complex and time consuming so the build will move much faster now that that the building has risen out of the ground. Columns and formwork for level 1 have commenced.

Please continue to check this site periodically for updates.

Click to view Ground Floor - concrete pour Click to view Level 1 - slab formation

News
Update

14 December 2018 - Crane up, basement excavation completed
& foundations underway

The tower crane has now been erected onsite.

Excavation of the basement has been completed and all retaining walls have been constructed.

Foundations and preparation for slab on ground are well underway.

Hamilton Marino Builders have now commenced onsite.

Please continue to check this site periodically for updates.

Click to view crane photo 1 Click to view crane photo 2 Click to view crane photo 3 Click to view crane photo 4 Click to view basement photo 1 Click to view basement photo 2 Click to view basement photo 3 Click to view basement photo 4

News
Update

16 October 2018 - Excavation reaches third basement
& Hamilton Marino Builders Appointed

Excavation is now progressing into the third basement level and beyond.

The top down slab/platform which will form the platform which the loading and unloading vehicles will use, has now been formed and poured and can be seen in the picture below.

We expect to reach the bottom level of the car park by the middle of November.

Hamilton Marino Builders have been officially appointed as builders and they will take over as soon as the excavation of the basement is completed.

Please continue to check this site periodically for updates.

Click to view photo 1 Click to view photo 2 Click to view photo 3

News
Update

10 September 2018 - Excavation Proceeding
& Hamilton Marino Builders Appointed

The piling and retention works have been completed for the site and excavation is proceeding.

Hamilton Marino Builders have also been formally appointed as builders.
Please continue to check this site periodically for updates.

Click to view photo

News
Update

17 May 2018 - Construction Management Plan Approved

Following approval of the Construction Management Plan by City of Manningham and Vicroads, piling and excavation of the basement carpark has now commenced onsite.
Please continue to check this site periodically for updates.

Click to view photo 1 Click to view photo 2

News
Update

06 April 2018 - The site has now been fully demolished after it took more than two months to obtain approval from the power authorities to abolish power in an abandoned building

We have served protection works notices and have the piling rig and excavators waiting on site to commence construction works.
We are currently awaiting approval of our Construction Management Plan which was lodged with City of Manningham in mid-December following which works will commence immediately.

Click to view photo 1 Click to view photo 2

600 Doncaster Road, DoncasterDelta Property group

DisclaimeruPrivacy policyuDue Diligence

Please note while every care is taken to ensure the contents of this website are correct, this information is to be used as a guide only. All images (including artist’s impressions) and plans are indicative only. Prospective purchasers should rely on their own enquiries, legal advice and the contract of sale. This site was completed prior to the completion of the design and construction of the project, therefore design, dimensions, fittings and specifications are subject to change. All areas are provided in accordance with the Method of Measurement for Residential Property provided by The Property Council of Australia. This does not represent the area on Title.